Construction Lien

Sammid J Mansoor

Case Conclusion Date:May 5, 2010

Practice Area:Contracts / Agreements

Outcome:Client is happy

Description:Client had a dispute with the performance of a subcontractors work, and the subcontractor refused to correct the problem. The client refused to pay and the subcontractor walked off the job and attempted to perfect a lien. We successfully negotiated terms for the subcontractor to correct and complete the work and the suit was dropped.