Case Conclusion Date: January 30, 2004
Practice Area: Personal Injury
Outcome: $475,000
Description: Defendant City of Seattle failed to ensure that proper shoring techniques were used during the trenching phase of a pipeline project. While working in the trench it collapsed causing steel plate to partially sever the plaintiff's forearm. Plaintiff was no longer able to work following the re-attachment of his arm.