Case Conclusion Date: March 31, 2006
Practice Area: Construction / Development
Outcome: Removal of Construction Lien
Description: We successfully argued for the removal of a construction lien from property owned by our client, Koby Coulon. The lien was removed from the land records upon our petition because it had been improperly filed, as notice requirements under the Private Works Act had not been met by the Contractor.