Case Conclusion Date: April 30, 2009
Practice Area: Construction / Development
Outcome: Construction Arbitration award of $139,000.00
Description: This case was against the builder of new residential home where a binding arbitration controlled any disputes. The arbitration award in favor of H. Hall, Petitioner, for $139,000.00 against J & J Homes, Respondent, was argued in front of Thomas E. Gostchall of Construction Arbitration Associates. Construction Attorney Duncan H. Adams successfully argued this case utilizing expert Maureen Davis, PE, of Haight Davis, and Brian Lamb of Georgia Fire and Restoration. This award was substantial in comparison to value of new residence.