How can a roofing company file a mech lien for cost of work not done?
You have two issues: (1) a contractor who has not worked out; and (2) threat of a mechanic's lien. I respond as follows. (1) You need a paper...
Dallas, TX
Construction and development Lawyer at Dallas, TX
Practice Areas: Construction & Development, Contracts & Agreements ... +2 more
You have two issues: (1) a contractor who has not worked out; and (2) threat of a mechanic's lien. I respond as follows. (1) You need a paper...
You have two issues: (1) a contractor who has not worked out; and (2) threat of a mechanic's lien. I respond as follows. (1) You need a paper...
Selected as the best answer
I assume that the construction work is for your house, and that your house is your homestead. For the house to be your homestead, the house has to...
Before you consider paying anything more to the first contractor, have him explain why more money is needed. Why didn't his work fix the problem...
The legal analysis would start with your contract. Some homebuilder contracts have escape provisions where the parties can agree to a mutual...
Unless your contract states that time is of the essence, and sets a completion deadline (with perhaps liquidated damages), the contractor has a...
You may not have a written contract, but you at least have an oral contract. An oral contract is as binding as a written contract - it is just...
A property owner typically is not responsible for injuries to independent contractors where the owner did not have control of the project. Texas...
These sorts of situations often come down to who has the best paper trail. So, you need to make sure that your paper trail is well...
Selected as the best answer
First, the title company probably is not liable for your mechanic's lien. The title company would have no liability if the title company excluded...