Archived
Contract from a vendor with a clause saying I have to pay $25000/ compensation to the vendor If I got fired from the client?
Brian's answer
|
Answered on May 17, 2018
The legal analysis would start with a review of the contract, and any associated paperwork.
To get a reasonable assessment, you would have to...
Under the Texas Property code 92.056,92.0561,92.056(f),92.0563
Brian's answer
|
Answered on May 16, 2018
The Property Code sections that you cite contain timelines for the repair / remedial work. It may be that the leased premises are uninhabitable. ...
Archived
Can I?
Brian's answer
|
Answered on May 16, 2018
You should consider preparing a letter to mail by certified mail, return receipt requested, to the restorer to set out the facts and to request the...
Archived
What are my options here?
Brian's answer
|
Answered on May 15, 2018
The legal analysis would start with your engagement agreement with your attorney, and the terms of the mediated settlement agreement.
You do not...
Archived
What is the best way to to require a general contractor to complete his contract so a non profit can obtain occupancy certific
Brian's answer
|
Answered on May 15, 2018
You should write the contractor a letter by certified mail to request that the contractor return to correct/complete his work. In that letter, you...
Archived
How do I get rid of a lien on my property in Texas?
Brian's answer
|
Answered on May 14, 2018
A subcontractor has requirements for perfecting a claim against the owner (or tenant). A subcontractor has to provide notice of non-payment to you...
Archived
What are my rights as a consultant when I am performing as I did as an employee?
Brian's answer
|
Answered on May 14, 2018
Despite being called a "consultant," you may still be an employee. As an employee, you have various rights under the Texas Payday Law. You can...
Is a contractor required to provide the homeowner with a final invoice, especially when the invoice is needed for a warranty?
Brian's answer
|
Answered on May 14, 2018
You should consider preparing a letter to mail by certified mail, return receipt requested to the contractor to set out the facts and to demand the...
Archived
What the options buyer have when builder did not comply with floor plan ?
Brian's answer
|
Answered on May 13, 2018
The legal analysis would start with a review of the contract that you signed, along with the associated paperwork.
You should check the total...
How long is a construction contract good for?
Brian's answer
|
Answered on May 13, 2018
The legal analysis would start with a review of the contract. If the contract does not provide for a date by which the notice to proceed is to...