Subcontractor under a fired General Contractor. Can I continue on the job?
You probably can safely work for the new GC, but get a written contract with him to protect yourself, and make sure you get paid. You could also...
San Francisco, CA
Construction and development Lawyer at San Francisco, CA
Practice Areas: Construction & Development, Arbitration ... +11 more
You probably can safely work for the new GC, but get a written contract with him to protect yourself, and make sure you get paid. You could also...
Yes, if he has not sued on the lien within 90 days of recording you can sue him for removal of the lien per Civil Code sec. 3154, and recover at...
This is not a legal question that a lawyer would be competent to answer. WOLFFLAW (415)788-1881
If you knew about the problem and did not disclose it, you made a mistake, but it should not be enough to cancel the sale. Maybe in exchange for a...
Selected as the best answer
Did you serve a preliminary notice on the owner? If so and the rest of the project is not yet complete, or there is no notice of completion or...
Sounds like you need to report him to the State Bar Association (calbar.org), and consult a legal malpractice attorney. WOLFFLAW (415)788-1881
There are a number of ways to do this. Since your are an S Corp the profits are typically distributed in proportion to share ownership, so you...
Ask them to give you a partial release of the stop notice. If you or they don't have the form we can provide you with one. Is this a public...
What is your question? Your inquiry is not intelligible. WOLFFLAW (415)788-1881
Yes, this information is typically made public by the SOS. The public can obtain copies under the Public Records Act and per the SOS. If...