Archived
I failed to complete my work release. I am supposed to turn myself in I had 9days left to finish my hours. What am I looking at?
Cathleen's answer
|
Answered on December 05, 2014
You posted this In the wrong place. This is the construction section. I will try to mark it for the right section for you but you should repost...
Archived
If I hire a GC to do foundation construction on my home that results in damage to the house next door - who is responsible?
Cathleen's answer
|
Answered on December 02, 2014
I agree that your contractor is primarily responsible for any damage to your neighbot's property caused by him or his subcontractors. However,...
Archived
This is regarding a cost overrun run up by a contractor doing a job for me on a time and materials basis.
Cathleen's answer
|
Answered on December 01, 2014
I', I'm not sure on what basis you'd be able to demand that the contractor pay you 1/2 the I'
I'm boxI''I what basis...
Archived
I need to file a stop Notice on a public works project. I have been reading up on it, but have lots of questions.
Cathleen's answer
|
Answered on December 01, 2014
This is a complicated area of the law. It sounds like there's a dispute about whether or not this change order was to be included in the contract...
Archived
Can I still file the mechanics lien? I am a licensed contractor and the work was completed half year ago.
Cathleen's answer
|
Answered on December 01, 2014
The answer depends on when the project as a whole was completed. The lien time runs from completion of the entire project, not just your work. So...
Archived
How do I proceed with the contractor who installed 850 sq ft of tile in my house and I noticed serious issues with quality?
Cathleen's answer
|
Answered on November 28, 2014
It sounds like this contractor has done a lot of things wrong. You need to put your demand in writing to the contractor and explain all of your...
Construction Bond Interpleader Process
Cathleen's answer
|
Answered on November 25, 2014
The law says the bond proceeds will be split among valid claimants. If the surety files an interpleader action, any claimant who doesn't file a...
Archived
Contractor delays cost me another month of mortgage. Can I withhold that loss of rent from remaining payment due to contractor?
Cathleen's answer
|
Answered on November 25, 2014
This is a tricky area. The first thing you need to do is look at your contract language. Then then are many variables to consider. Did you add any...
Archived
Re: 20 day preliminary notice. Owner wouldn't pay last week of project plus other purchases/equipment rentals made earlier .
Cathleen's answer
|
Answered on November 22, 2014
It depends on who your contract is with. If it's with the owner, you can lien for the amount covered under the preliminary notice and sue for...
Selected as the best answer
Archived
Can put lien on property already have 1&2 lien from lender
Cathleen's answer
|
Answered on November 21, 2014
I agree that your question is confusing. If your question is whether or not a contractor can lien your property even if other liens are on that...