How to collect spousal support lien in Montana from Calif.?
This is posted in the wrong section. I will re-post it for you in the Family Law section.
Millbrae, CA
Construction and development Lawyer at Millbrae, CA
Practice Areas: Construction & Development
This is posted in the wrong section. I will re-post it for you in the Family Law section.
The time for recording a lien runs from completion of the entire project, not just Contractor A's work. So unless the work stopped for a long time...
If the sub did not properly and timely serve you with a preliminary notice, the sub does not have any lien rights against your property. Any late...
Unlicensed contractors cannot lien a job or file a legal action to collect money owed for jobs over $500 which required a contractor's license. In...
A preliminary notice is required to lien where you were hired by the general contractor. You can make a claim against the general contractor's...
It does not make sense that your insurance company would have paid over $100K to these contractors with no work being done. The best way to speed...
The general contractor is responsible for the work done by his subcontractors, employees, and agents. Make sure that you write the contractor a...
You can file in SF because that's where the contract was performed. Good luck!
You will need to review terms of the contract and see what it requires the contractor to do. The contractor should have known that the ceiling...
Yes, your lien will become invalid after 90 days if you don't file a lawsuit to foreclose the lien. However, if the lien period hasn't yet run,...