Archived
Direct contractor (A) gets fired from the job. New contractor (B) hired to continue job. Direct contractor A seeks to file lien
Cathleen's answer
|
Answered on October 27, 2016
The time for recording a lien runs from completion of the entire project, not just Contractor A's work. So unless the work stopped for a long time...
Archived
What is our obligation to a subcontractor after GC skipped town?
Cathleen's answer
|
Answered on October 25, 2016
If the sub did not properly and timely serve you with a preliminary notice, the sub does not have any lien rights against your property. Any late...
Archived
How can I get paid for windows I installed and completed? I am a unlicensed handyman.
Cathleen's answer
|
Answered on October 25, 2016
Unlicensed contractors cannot lien a job or file a legal action to collect money owed for jobs over $500 which required a contractor's license. In...
Can I file mechanic's lien without preliminary notice?
Cathleen's answer
|
Answered on October 25, 2016
A preliminary notice is required to lien where you were hired by the general contractor. You can make a claim against the general contractor's...
Archived
Re: House Fire / Contractors
Cathleen's answer
|
Answered on October 25, 2016
It does not make sense that your insurance company would have paid over $100K to these contractors with no work being done. The best way to speed...
Archived
Bad craftsmanship question
Cathleen's answer
|
Answered on October 25, 2016
The general contractor is responsible for the work done by his subcontractors, employees, and agents. Make sure that you write the contractor a...
Archived
I would like to file a claim in small claims court. What city should I file the claim in?
Cathleen's answer
|
Answered on October 24, 2016
You can file in SF because that's where the contract was performed. Good luck!
Archived
Do I have to pay the contractor for a patio installed incorrectly?
Cathleen's answer
|
Answered on October 22, 2016
You will need to review terms of the contract and see what it requires the contractor to do. The contractor should have known that the ceiling...
Will my filing of mechanics lien be void if i don't file a lawsuit within 90 days?
Cathleen's answer
|
Answered on October 21, 2016
Yes, your lien will become invalid after 90 days if you don't file a lawsuit to foreclose the lien. However, if the lien period hasn't yet run,...
My contractor has overcharged me to remodel 2 bathrooms. Our original contract stated a certain amount for labor and materials.
Cathleen's answer
|
Answered on October 19, 2016
There are obviously some serious problems going on here. By law a home remodel contractor is not allowed to do any extra work without a signed...