My tile contractor wants to receive the final balance due before he finishes work not done.
I agree with other counsel that you don't have to pay for work not completed. Be sure that you've put in writing your complaints about his work...
Millbrae, CA
Construction and development Lawyer at Millbrae, CA
Practice Areas: Construction & Development
I agree with other counsel that you don't have to pay for work not completed. Be sure that you've put in writing your complaints about his work...
No, you can't legally record a mechanic's lien for just paying a bill for the company. You're also too late to file a lien if this was done 5...
If you received a timely valid preliminary notice via certified mail from the supplier and the roofing company, then they have lien rights on your...
The apartment manager or owner should have a certificate of insurance from the contractor that gives his insurance information. Ask them for a...
Theoretically speaking, it's possible for a construction consultant to get sued for liability relating to a construction project, and to...
I agree with other counsel that you can't sue for labor OR materials if you were an unlicensed contractor and the value of the work was more than...
I agree with counsel that it depends on the Building Code. If the windows you installed did not comply with the Code, then the Building Dept. can...
Hopefully you have some documentation that you received from the contractor to prove they did the work, like a written contract, invoice or...
I would simply call up the suppler and tell them they made a mistake in sending you the preliminary notice, and that they need to correct their...
I agree with other counsel that you should immediately file a complaint against the contractor with the Contractor's State License Board. The...