I received CA preliminary notice on April from a plumber who did not do the job on Jan.
It's probably too late for the plumber to put a lien on, and it's doubtful whether repair work would qualify as a permanent work of improvement ...
Millbrae, CA
Construction and development Lawyer at Millbrae, CA
Practice Areas: Construction & Development
It's probably too late for the plumber to put a lien on, and it's doubtful whether repair work would qualify as a permanent work of improvement ...
A subcontractor is required to serve an owner, the general contractor, and the lender (if any) with a Preliminary Notice. The preliminary notice...
First of all, a contractor is required to have a written contract for home improvement work, so this will be an issue for the contractor with the...
I agree that going to Small Claims court would be the most cost-effective method to get a judgment against the unlicensed contractor. Once. You...
A preliminary notice is not a lien but it's often the first step. If you hired the plumber directly he doesn't need to send you a preliminary...
This is a duplicate of the first question I just answered. In addition, however, you may also want to consider making a claim against the...
I think it would be best to have a construction attorney write a demand letter to the contractor for you threatening him with legal action if he...
The first thing you should do is make sure that you've sent a letter to the contractor demanding that he return and finish the job, and keep a copy...
I agree that you may be able to hold the builder liable but more information is needed. This can be a complicated matter. It's best to consult...
It's most likely too late to file a lien unless your work was part of a larger overall construction project that is not finished yet or finished...