CALIF/ Does the Preliminary Notice need to be served prior and separately from the Mechanics Lien?
It is possible it is valid depending on when the work was initiated and when it was finished. A valid preliminary notice covers labor and materials...
Los Angeles, CA
Construction and development Lawyer at Los Angeles, CA
Practice Areas: Construction & Development, Business ... +3 more
It is possible it is valid depending on when the work was initiated and when it was finished. A valid preliminary notice covers labor and materials...
No, the right to record a lien has passed. You will need pursue the credit card company claim and/or a breach of contract action against your...
Ask for your contractor to provide you with a Conditional Waiver and Release Upon Final payment completed by the supplier before making your next...
Yes, you can sue the license bond surety and your contractor to try to recover up to $15,000.00. It would be interesting to know why the surety...
The civil code allows you to file a petition to remove the Mechanics Lien and recover your attorney’s fees. It may be a good idea to first demand...
Though the indemnity provision you quoted from appears to be overbroad, it likely means that if there are claims as a result of your work (e.g.,...
Assuming the project is still ongoing or has been recently completed (within the last 90 days), you likely have a valid mechanics lien right, and...
Assuming you were properly licensed and completed your work within the last 90 days, you may still be able to record a mechanics lien. You can...
Assuming you are properly licensed, I would record a lien; it is amazing how fast an owner will get you paid when you enforce your constitutional...
It will depend on what your contract says (or does not say). If the hall is trying to charge you more because they added air conditioning and want...