Can the lien be refilled after its 90 day expiration? How will the lien effect my credit?
If it has been 90 days from "completion" of the work (or 90 days from a 60 day period of continuous cessation of labor on the job), any lien...
Los Angeles, CA
Construction and development Lawyer at Los Angeles, CA
Practice Areas: Construction & Development, Business ... +3 more
If it has been 90 days from "completion" of the work (or 90 days from a 60 day period of continuous cessation of labor on the job), any lien...
One of the initial issues that will need to be solved is the relationship between the "third party" and the owner. It is possible to circumvent...
When was the mechanics lien recorded?
I do not believe a portable restroom (that is not connected to a "work of improvement") is the subject of a proper mechanics lien. I do not...
It depends on whether you can make the good faith argument that you had a direct contractual relationship with the owner. If you had such a direct...
I think you can argue this either way, but if I was the contractor or supplier's advocate, I would argue that the the stop payment notice is...
Yes, this is done from time to time on private works of improvement. In fact, the owner posting project security for the benefit of the contractor...
No, he cannot properly lien your house for work performed 3 years ago. It is possible that he MAY have a breach of contract action, however.
While the lien itself will secure the reasonable value of the labor and materials furnished to to the project or the contract price (whichever is...
There may be serious disgorgement penalties in play so it is important to speak to experienced legal counsel as soon as possible.