Aero Construction Co. Inc. v. Ledcor Construction Inc., et al.
Dec 08, 2010OUTCOME: Verdict then settlement
Claim for non-payment by our client (general contractor, Ledcor) and its subcontractors, stemming from stalled Fauntleroy Place project in West Seattle. Ledcor's claims included breach of contract, li ... en enforcement and violation of Uniform Fraudulent Transfers Act. At first trial, our client (Ledcor) was among the prevailing parties and was awarded a total of $4,444,371.40 plus post-judgment interest. The case settled approximately six months later and the terms of the settlement are confidential.