San Francisco Bay Area Rapid Transportation Distrct v. PPF Industrial, et al.
Jan 26, 2015OUTCOME: Case resolved for $42,750,000
Eminent domain action to condemn a large industrial warehouse and distribution center.
Costa Mesa, CA
Real estate Lawyer at Costa Mesa, CA
Practice Areas: Real Estate, Land Use & Zoning
OUTCOME: Case resolved for $42,750,000
Eminent domain action to condemn a large industrial warehouse and distribution center.
OUTCOME: Case resolved for: $6.4 million
Represented owners of three ocean- and pastoral-view parcels totaling 13.47 acres off Highway 1 in San Simeon. Caltrans sought to condemn portions of two of the three parcels for its State Route 1 Rea ... lignment Project. Caltrans initially offered $1,073,800. It later valued total compensation for the part takes at $4,000,200. Caltrans ultimately agreed to pay $6,440,000 for full takes of two of the parcels, preserving the owners' ability to seek compensation for the taking of, and damages to, the third parcel.
OUTCOME: The case resolved for $15.4 million
Represented the landowner in an eminent domain action brought by the City of Lake Forest. The City condemned a little over 13 acres for a new sports park. The city valued just compensation for the ex ... pert exchange at $6.665 million. The case settled for $15.4 million.
OUTCOME: Case resolved for $4,500,000
Represented ARAMARK in an action brought by Caltrans to acquire one of ARAMARK's key market centers for the I-215 widening project. Caltrans' initial offer was $1,881,000.
OUTCOME: Case resolved for $1,671,000
Represented Requip, a large construction-equipment broker, in an action by the City of Fontana to acquire a portion of Requip's property for a freeway overpass project. The City's pre-litigation offer ... was $916,000.