Can someone I hired to build kitchen cabinets for one of my customers put a lien on his property?
Don's answer is on point. Furthermore, due to the fact that no permit was involved in this job, it is also highly likely that there is no notice...
Jacksonville, FL
Construction and development Lawyer at Jacksonville, FL
Practice Areas: Construction & Development, Litigation ... +7 more
Don's answer is on point. Furthermore, due to the fact that no permit was involved in this job, it is also highly likely that there is no notice...
Assuming that your last day on the job was august of 2010 and that you did not record a lien already, you cannot record a valid lien at this point....
Agree with prior responses. However, you need to review the construction contract to determine if this risk was allocated within the terms of the...
While I am not familiar with the construction law in your state, based on the facts in your question, I agree with the comments so far and you...
I am not licensed in Texas but most states have statutory conditions precedent that a potential lienor, such as your business, must satisfy in...
Depending on the county, you may be able to pull the permit as the owner. You will have to pay a penalty for failing to pull the permit initially....
Selected as the best answer
To have a valid lien against your property, the sub, with whom you do not have contractual privity, must serve (via certified mail) a document...
If you properly issued the notice of contest and no legal action has been filed by the lienor, then the lien has expired per the statute. See...
If you properly issued the notice of contest and no legal action has been filed by the lienor, then the lien has expired per the statute. See...