J.R. Hale Contracting Co., Inc. v. Union Pacific Railroad
Jan 01, 2008OUTCOME: Grant of summary judgment reversed and remanded
Appeal from grant of summary judgment enforcing releases to bar claims for additional work performed. 2008-NMCA-037
Albuquerque, NM
Construction and development Lawyer at Albuquerque, NM
Practice Areas: Construction & Development
OUTCOME: Grant of summary judgment reversed and remanded
Appeal from grant of summary judgment enforcing releases to bar claims for additional work performed. 2008-NMCA-037
OUTCOME: District Court ruling assuming jurisdiction was reversed and the case remanded to the district in which the administrative bid protest hearings were held.
Writ of Mandamus arising from litigation filed by disappointed bidder. 2008-NMSC-047
OUTCOME: The claim of lien of Richardson & Richardson was a valid security interest in the leasehold estate and was not subject to a preference action.
Appeal from Bankruptcy Court regarding enforceability of claims of lien against leasehold interests and avoidance of bankruptcy preference action. 315 B.R. 776
OUTCOME: Garnishee not entitled to contract payments
Court of Appeals decision regarding liability of general contractor on writ of garnishment against contract payment application funds due to subcontractor. 2002-NMCA-11; 2001 N.M. App. LEXIS 117