• State ex rel. Lighting and Power Services, Inc. v. Interface Construction Corp., 553 F.3d. 1150 (8th Cir. 2009)
Jan 01, 2009OUTCOME:
Plaintiff sub-subcontractor sued defendants, a general contractor, a subcontractor, and a payment bond issuer, in the United States District Court for the Eastern District of Missouri under 40 U.S.C.S. ... § 3131(b)(1) of the Miller Act to recover payment for labor and materials. The district court denied the general contractor's motion to compel arbitration. The general contractor filed an interlocutory appeal. The 8th Circuit affirmed the decision of the District Court.