Creekview Interconnection Project, PSCW Docket No. 137-CE-177
Feb 16, 2015OUTCOME:
Construction of 6-mile, double-circuit 138 kV line to support new distribution substation (~$26 million), Wisconsin CPCN
Waukesha, WI
Energy and utilities Lawyer at Waukesha, WI
Practice Areas: Energy & Utilities, Mediation ... +2 more
OUTCOME:
Construction of 6-mile, double-circuit 138 kV line to support new distribution substation (~$26 million), Wisconsin CPCN
OUTCOME:
Rebuild of ~7 miles of 69 kV line, including abandonment of ~15 miles of line (~$24 million), Wisconsin CA
OUTCOME:
Extension of 0.4-mile existing 69/138 kV double-circuit line and construction of new, 0.3-mile 69 kV transmission line to support new substation (~$14 million), Wisconsin CA
OUTCOME:
Rebuild of 20-mile, 69 kV line (~$38 million), Wisconsin CA
OUTCOME:
Rebuild of 45-mile, 69 kV lines ($51 million), Wisconsin CA
OUTCOME:
Construction of two 48-mile, 138/345 kV parallel lines (~$327 million), Wisconsin CPCN
OUTCOME:
Construction of 60-mile, 138 kV line (~$132 million), Michigan CPCN
OUTCOME:
OUTCOME:
OUTCOME:
Madison area transmission line siting proceeding