San Bernardino Associated Governments (SANBAG)
Jan 01, 2014OUTCOME: Necessary Properties Delivered on TIme and Under Budget
Represented SANBAG with acquiring portions of 150+ properties for the sbX E-Street Corridor Bus Rapid Transit Project, a 15.7-mile bus rapid transit line in the Inland Empire. Mr. Kuhn was able to sec ... ure possession of the entire right of way on an incredibly ambitious schedule to ensure the project secured necessary FTA funding. Mr. Kuhn also ensured all property rights were obtained under project budget.