Archived
I'm a contractor. Just installed a bathroom and if the customer does pay the last payment, can I remove installed items?
Karl's answer
|
Answered on November 15, 2014
I agree with the others -- how are you going to get access?
On residential projects you have 4 months from the last work to file a mechanic's...
Contractor Stopped Showing Up To Finish A Job. First Floor Incomplete, Basement Untouched. What Are My Options?
Karl's answer
|
Answered on June 06, 2014
If a home improvement contractor takes money in advance of performing the work, the contractor has to hold the money in escrow -- these are trust...
Archived
Served with a mechanics lien from a subcontractor who first claimed 1766 and now wants 2266. Contractor says he paid him. help
Karl's answer
|
Answered on May 26, 2014
The amount in dispute is too low to justify a lot of legal work.
If you paid the general contractor in full prior to notice of the lien then you...
Archived
Mechanics Lien Lawsuit:
Can I sue my client for non-payment of architectural services without a written contract.
Karl's answer
|
Answered on May 15, 2014
It sounds like you are in a good position. Verbal contracts are just as enforceable as written contract -- except in circumstances not relevant...
Archived
I feel a contractor over charged me for work done.
Karl's answer
|
Answered on March 15, 2014
Respecting the contract price, once you sign a contract you are mostly stuck with the price unless you can show the price was "unconscionable" --...
Ad