My remodel contract states contractor will pull the permits. Do ALL permits need to be pulled before starting?

Asked over 2 years ago - Los Angeles, CA

We are 2 months into project, and I found out only one permit has been pulled. Do all permits need to be pulled in the beginning of the project, or can they pull later? There will be electrical, mechanical, plumbing and roof permits at the least (new addition (bed/bath) and remodel existing bathroom, along with Central heating system and electrical box upgrade). Since he has only pulled one permit, but has collected payment (based on our progress payments) for completing, can I cancel our contract? If so, what would be my reason?

Attorney answers (3)

  1. David Thien Tran

    Contributor Level 11

    3

    Lawyers agree

    Best Answer
    chosen by asker

    Answered . Permits are done sequentially, not all together on a remodel for a variety of reason, some of which depends on what is actually behind the walls when the contractor get to work. If the project is a larger remodel, the city usually wants the specialty contractors to pull the permits themselves so that the city can have their licenses, identities and specialties on file.

    Alternatively, on smaller jobs, contractor can pull a combo license to save time. It depends on the city where the job is.

    As for ending the contract, the contract document determines your rights and risks. First, check to see if the contract complies with the home improvement contract of 2006 as required in the CA Bus & Prof Code 7159. If it does not, you can terminate contract and demand all monies paid out. If it does comply with the codes, then you may be stuck with paying for reasonable services performed (including plans & permits).

    If you terminate contract without finding out the terms, you may have breached the contract.

    You may want to hire counsel for this one.

  2. Christopher J McKillop

    Contributor Level 7

    3

    Lawyers agree

    Answered . Did you want to cancel the contract? If so, why? Lets answer that
    question. It can't really be due to failing to pull a permit. However, its
    customary to disclose to the local jurisdiction having authority the full
    scope of the project and paying all permits up front. But you can always
    add some permits as you go, as long as you pull them before starting that
    type of work, ie, no wiring until you have the electrical permit, etc.

    This answer is not intended as legal advice nor does it create an
    attorney-client relationship.


    Chris McKillop
    Rogers Machinery Co., Inc.
    14650 SW 72nd Ave.
    Portland, Oregon 97224

    Phone: 503-639-0808
    --------------------------------Legal Disclaimer------------------------
    This communication is intended for the recipient identified above and no other person or entity. Any dissemination, distribution or copying of this communication is a violation of federal copyright law and is strictly prohibited without our consent. Please call us if you have received this in error. Copyright 2008, Rogers Machinery Co., Inc. All Rights Reserved.

  3. Frank Wei-Hong Chen

    Contributor Level 20

    1

    Lawyer agrees

    1

    Answered . All permits do not necessarily need to be pulled before commencing work. This is often because permits have an expiration date. Thus, you would not be able to cancel the contract with the contractor on this basis.

    Frank W. Chen is licensed to practice law in the State of California. The information presented here is general in... more

Can't find what you're looking for? Ask a Lawyer

Get free answers from experienced attorneys.

 

Ask now

22,408 answers this week

2,822 attorneys answering

Ask a Lawyer

Get answers from top-rated lawyers.

  • It's FREE
  • It's easy
  • It's anonymous

22,408 answers this week

2,822 attorneys answering