West Coast Air Conditioning Co., Inc. v. Fountain Valley School District

Case Conclusion Date: 01.01.2008

Practice Area: Construction & Development

Outcome: Client was paid $1.2 million for delay and disruption damages, and received a thank you letter from the District for building a quality construction project.

Description: Prime contractor on a $12.875 million four school modernization project suffered delay, disruption, and inefficiency damages as a result of unclear plans and specifications, and late completion of predecessor activities by other contractors to the District. The firm filed suit to collect the damages. Following over a year of litigation and cordial meetings with the District, its counsel, and its experts to explain the claim, the case was mediated to a settlement with the firm’s client.