Description: Successfully established that contractor’s $31,000 mechanics’ lien had priority, by three days, over bank’s $2.4 million mortgage interest. Also convinced Court that opposing counsel had committed sanctionable conduct. The Court’s order awarded the full value of the lien along with more than $23,000 in costs, disbursements, attorneys’ fees, and interest.