The project is at substantial completion but has not filed notice of completion yet, and yes, we did file a preliminary notice at the beginning of the project. Do I send the stop notice to the bonding Co as well?

George William Wolff
George William Wolff, Construction / Development Lawyer - San Francisco, CA
Posted over 1 year ago.

No, the bond claim is a separate process.

Serve the public entity/school and the general contractor by certified or registered mail.

Better file it sooner than too late!!!


You have to file suit on the stop notice or it expires and becomes useless.

See the Article/table from our website:

http://www.wolfflaw.com/files/1_deadlines-for-perfecting-a-stop-notice-03-29-11.pdf

George William Wolff
George William Wolff, Construction / Development Lawyer - San Francisco, CA
Posted over 1 year ago.

No, the bond claim is a separate process.

Serve the public entity/school and the general contractor by certified or registered mail.

Better file it sooner than too late!!!


You have to file suit on the stop notice or it expires and becomes useless.

See the Article/table from our website:

http://www.wolfflaw.com/files/1_deadlines-for-perfecting-a-stop-notice-03-29-11.pdf

George W. Wolff, attorney
Law Office of George W. Wolff
505 Sansome Street, Suite 1525
P.O.Box 26749
San Francisco, CA 94126-6749
Telephone: (415)788-1881, ext.222
Telecopier: (415)788-0880
e-mail: george@wolfflaw.com
website: www.wolfflaw.com

IMPORTANT NOTICE: This message is intended only for the individual, business or entity to which it is addressed. It contains information from an attorney which may be private, privileged, confidential and/or protected or exempt from disclosure or dissemination under State of Federal Law. If you are not the addressee or intended recipient, please be aware that any dissemination , distribution, use, disclosure or copying of this communication is strictly prohibited. Please contact us immediately if you are not the addressee or intended recipient

No photo
Asker
Posted over 1 year ago.

Thank you for the info... when looking at the timeline you provided the link to it appears that this was updated March of 2011... is that correct? Or has this been updated to match the new law dated July 2012?

George William Wolff
George William Wolff, Construction / Development Lawyer - San Francisco, CA
Posted over 1 year ago.

The section numbers of the law have changed but the times and deadlines have not

George W. Wolff, attorney
Law Office of George W. Wolff
505 Sansome Street, Suite 1525
P.O.Box 26749
San Francisco, CA 94126-6749
Telephone: (415)788-1881, ext.222
Telecopier: (415)788-0880
e-mail: george@wolfflaw.com
website: www.wolfflaw.com

IMPORTANT NOTICE: This message is intended only for the individual, business or entity to which it is addressed. It contains information from an attorney which may be private, privileged, confidential and/or protected or exempt from disclosure or dissemination under State of Federal Law. If you are not the addressee or intended recipient, please be aware that any dissemination , distribution, use, disclosure or copying of this communication is strictly prohibited. Please contact us immediately if you are not the addressee or intended recipient